Jomax Water Reclamation Facility
Project
Description
The Jomax Water Reclamation Facility expansion
will increase treatment capacity from the current 0.75 million
gallons per day to 2.25 million gallons per day. The facility is
located just north of the Beardsley canal, west of the Agua Fria
River, and will serve the Vistancia development and future
development in the area.
Project at a Glance
|
Lead Agency |
City of Peoria
Joe Kurrus (Peoria Utilities Project Manager)
Phone: 623-773-7753
E-mail:
Joe.Kurrus@peoriaaz.gov |
|
Design Consultant |
Wilson and
Company (www.wilsonco.com) |
|
Contractor |
MGC Contracts (www.mgccontractors.com) |
|
Project Budget |
$17 Million |
|
Funding Sources |
Water
Development Impact Fees
Wastewater Development Impact Fees
Vistancia Community Facilities District
Development Bonds |
Project
Status
The project
construction is completed
|
Design |
0% |
|
|
Land
Acquisition |
0% |
|
|
Construction |
0% |
|
Document Downloads