Project Description
This water reclamation facility will serve the southern Peoria area of the city and will treat wastewater for beneficial reuse. The plant is being designed to treat 10 million gallons per day (mgd) with the potential to expand to 13 mgd in the future. The facility will be located at 79th Avenue and Butler Drive (South of Olive Ave.)

Project at a Glance

Lead Agency City of Peoria
Shawn Kreuzwiesner (Peoria Utilities Project Manager)
Phone: 623-773-7286 #3
E-mail: shawn.kreuzwiesner@peoriaaz.gov
Design Consultant Black and Veatch
Brad Hemken
Phone: 602.381.4400
Email: hemkenbe@bv.com
Project Consultant Jim Kaylor
Phone: 623-221-4204
Email: jkaylor@hotmail.com
Construction Manager @ Risk SUNDT Construction
Andrew Apostolik
Email: agapostoli@sundt.com 
Project Budget $121 Million
Funding Sources Capital Improvement Program
Status Updated 6/1/2007
Construction Start Date 7/2006
Completion Date Fall of 2009

Project Status
SUNDT Construction has been selected for Construction Manager @ Risk, and construction started in July 2006 and is expected to be completed in the Fall of 2009.

Design Phase 100%
25% 50% 75% 100%

 

                                     
Construction Phase 45%
25% 50% 75% 100%

 

                                     

Document Downloads

Links

View a picture slideshow by clicking on the image
View a picture slideshow by clicking on the image on the left.

 

 

Copyright © 2006 City of Peoria - All Rights Reserved