US60 (Grand Avenue)
99th Avenue
to 83rd Avenue
Project Description
This project is part of an overall project being administered by
the Arizona Department of Transportation (ADOT) and the Regional Transportation
Plan (RTP) which includes funding to widen US60 (Grand Avenue) by
one lane in each direction along various segments between Loop 303
and Interstate 17 to create a continuous six-lane arterial by 2011.
Other unspecified improvements to improve traffic flow on Grand
Avenue are included in later phases of the 20-year Transportation
Plan. This particular segment within the City of Peoria, as
defined by ADOT, is from 99th Avenue to 83rd Avenue.
The segment from 99th Avenue to
83rd Avenue includes the following types of improvements:
-
Widening of Grand Avenue to 6
lanes (3 lanes each direction)
-
Loop 101 and New River Bridge
Improvements
-
Intersection Improvements at
91st Avenue and Grand Avenue to include dual left turn lanes for
eastbound Grand Avenue to northbound 91st Avenue
-
Construction of a new sidewalk
along the east side of 91st Avenue at the BNSF Railroad Crossing
-
Storm Drain Improvements
-
Utility Modifications
Project at a Glance
|
Lead Agency |
Arizona Department
of Transportation
Mohammed Zaid
Phone: 602-712-8467
E-mail:
MZaid@azdot.gov |
|
Design Consultant |
URS Corporation |
|
Contractor |
To be determined |
|
Project Budget |
$10 Million
(Construction) |
Project
Status
Currently this segment is in the final design
stages. The current schedule, as determined by ADOT, is
for the design to be completed by fall/winter 2008 with
construction starting in early 2009 and ending in early 2010.
Please refer to the ADOT website for current project status and
updates.
|
Design |
95% |
|
|
Construction |
0% |
|