Thunderbird Rd Widening, Loop 101 to 94th Dr
Project
Description
This project will provide
additional capacity and enhance safety on Thunderbird Road
between the Loop 101 and 94th Drive. The southern half of the
roadway (the eastbound lanes) will be expanded from two to three
lanes along this entire stretch of 94th Avenue to Loop 101, while the northern half (the
westbound lanes) will be expanded from two to three lanes
between the Loop 101 and 91st Avenue. The bridge over the New
River will also be widened to accommodate the additional lanes.
Other planned improvements include a raised landscaped median, a
10-foot sidewalk on the north side, either a six-foot or
eight-foot sidewalk on the south side, and bike lanes from 91st
Avenue to Rio Vista Boulevard.
Project at a Glance
|
Lead Agency |
City of Peoria
Geoffrey Zinnecker (Peoria Project Manager)
Phone: 623-773-7212
E-mail:
Geoffrey.zinnecker@peoriaaz.gov |
|
Design Consultant |
URS |
|
Contractor |
FNF Construction,
Inc. |
|
Project Budget |
$17,620,000 |
|
Funding Sources |
|
Project
Status
The City's design
consultant submitted the final Design Concept Report in August
2006. The Notice to Proceed for the design was issued on October
4, 2006 and is expected to take 12 months. The City is working
to acquire the necessary right of way for the project. The
anticipated start date for construction is fall 2007. A
copy of the Design Concept Report (DCR) is available upon
request.
|
Design |
90% |
|
|
Land
Acquisition |
80% |
|
|
Construction |
5% |
|