Signalize 103rd Avenue and Northern Avenue

Project Description
The City of Peoria has determined that a signal is warranted at the intersection of 103rd Avenue and Northern Avenue.  The project includes not only signals for the intersection, but a waterline extension and a connection to the existing utility lines.  Although the roadway is generally built out, both the north and south approaches will require pavement changes. 

The south leg of 103rd Avenue is in the City of Glendale and they have been partnering with the City of Peoria to insure that he changes to their road meet their requirements. 

The north leg of 103rd Avenue will need to be widened which will require the acquisition of right-of-way on the north east corner.

Project at a Glance

Lead Agency City of Peoria in partnership with the City of Glendale
Geoffrey Zinnecker (Peoria Project Manager)
Phone: 623-773-7293
E-mail:
Geoffrey.zinnecker@PeoriaAz.Gov
Design Consultant AMEC
Contractor CS, Construction, Inc.
Project Budget $725,000.00
Funding Sources

General Obligation Bonds

Project Status Schedule
Present the project to City Council in the winter, 2008.

Finish construction in the summer, 2009.

Design 95%
25% 50% 75% 100%

 

                                     
Land Acquisition 10%
25% 50% 75% 100%

 

                                     
Construction 0%
25% 50% 75% 100%

 

                                     