Rose Garden Lane Drainage Channel
Project Description
The Rose Garden Lane
Channel is one of several individual drainage projects
recommended in the Glendale-Peoria Area Drainage Master Plan.
The purpose of this project is to intercept drainage north of
Rose Garden Lane and west of 95th Avenue and convey the flow to
the Agua Fria River. Project elements include a drainage
channel, box culverts, laterals, catch basins, and a large
retention basin.
Project at a Glance
|
Lead Agency |
City of Peoria
Burton Charron (Project Manager)
Phone: 623-773-7210
E-mail: Burton.Charron@PeoriaAz.Gov |
|
Partner Agency |
Flood Control
District of Maricopa County
Don Rerick (Project Manager)
Phone: 602-506-4878 |
|
Design Consultant |
Wood Patel |
|
Contractor |
N/A |
|
Project Budget |
$8,819,883 |
|
Funding Sources |
|
Project
Status
Construction is underway and is expected expected to be
completed in the Fall, 2008.
Feel free
to call the Rose Garden Lane Drainage Channel Project 24-hour
Construction Hotline number at 623-606-2329 for any questions
related to the project.
|
Design |
100% |
|
|
Land
Acquisition |
95% |
|
|
Construction |
60% |
|
Links
Last
Updated:
Wednesday April 16, 2008 10:54 AM
|