Drainage Improvements: 83rd Avenue and Pinnacle Peak Road

Project Description
The 83rd Avenue and Pinnacle Peak Road Drainage project is one of several individual drainage projects recommended in the Glendale-Peoria Area Drainage Master Plan. The purpose of this project is to capture drainage in the area north of Pinnacle Peak Road between 83rd and 91st Avenues and convey it to the existing drainage infrastructure at Deer Valley Estates and from there to the New River. Project elements include a storm drains, laterals, catch basins, and two large retention basins.
 

Project at a Glance

Lead Agency Flood Control District of Maricopa County
Mark Lewis (Project Manager)
Phone: 602-525-6786
Partner Agency City of Peoria
Burton Charron (Project Manager)
Phone: 623-773-7210
E-mail the Project Manager
Design Consultant Jacobs Civil, Inc.
Contractor N/A
Project Budget $3,374,039 (City Share)
Funding Sources
  • Flood Control District of Maricopa County (50%)

  • General Obligation Bonds

Project Status
Construction is underway and is scheduled to be complete in July, 2008.

Design 100%
25% 50% 75% 100%

 

                                     
Land Acquisition 100%
25% 50% 75% 100%

 

                                     
Construction 75%
25% 50% 75% 100%

 

                                     