Beardsley Connection to Loop 101
-
Project
Description
The Beardsley Road Extension project will provide additional access to the
Loop 101 from the northern portion of the City of Peoria and the northwest
valley. This will be accomplished by extending Beardsley Road from 81st
Avenue across the New River via a bridge to a one-way frontage road, which
starts at the 75th Avenue traffic interchange and terminates at the Union
Hills Drive interchange. A bridge over Loop 101 north of Union
Hills Drive will allow frontage road traffic to access the northbound lanes
of Loop 101 without having to go through the signalized interchange at Union
Hills Drive.
Public Open House Briefing
The City of Peoria, City of Glendale and Arizona Department of
Transportation will be conducting two open house briefings on
Wednesday, May 28, 2008 from 6:00 pm to 8:00 pm at Sunrise
Mountain High School and on June 3, 2008 at the Community Church
of Joy. Representatives from each agency will attend, and
information will be available about the final design and
construction schedules.
Public Open House Information Flier
Project at a Glance
|
Lead Agency |
City of Peoria
Chris Kmetty (Peoria Project Manager)
Phone: 623-773-7247
E-mail:
Chris.Kmetty@PeoriaAz.Gov |
|
Review Agency |
Arizona Department
of Transportation (ADOT)
Ron McCally (ADOT Project Manager)
Phone:
602-712-7646 |
|
Partner Agency |
City of Glendale
Horatio Skeete (Deputy City Manager)
Phone:
623-930-2254 |
|
Design Consultant |
Jacobs |
|
Contractor |
N/A |
|
Project Budget |
$30,672,916 |
|
Funding Sources |
|
Project
Status
The City's design consultant submitted the final
design concept report and 30 percent plans in July 2006. Shortly
after these plans were submitted, City engineers participated in
a three-day value engineering session with a separate
engineering firm to evaluate the plans and discuss additional
final design recommendations. The City of Peoria in conjunction
with the City of Glendale and ADOT are currently completing
designs for Phase I and Phase II as well as 83rd Avenue Median
and the Beardsley Trailhead. The City is also working to
acquire the necessary right of way for the project. Funding for
construction is available in fiscal years 2008 and 2009. The
anticipated construction start date is winter 2008.
Project Phasing and CMAR
Selection Information
The
Beardsley Connector Project is broken into four separately
funded projects. Beardsley Road Extension Phase I and
Phase II (PW00152), 83rd Avenue Median (EN00207), New River
Beardsley Road Trailhead (CS00121) and the Union Hills TI
(Traffic Interchange) Reconstruction and Widening (EN00274). Phase II of the
Beardsley Connector contained within the ADOT right-of-way and
the Union Hills TI reconstruction will be constructed by ADOT
and is NOT part of this solicitation. This solicitation
will include Beardsley Connector Phase I, 83rd Avenue Median and
New River Beardsley Road Trailhead.
|
Design |
80% |
|
|
Land
Acquisition |
50% |
|
|
Construction |
0% |
|