91st
Avenue and Olive Avenue Intersection Improvements
Project
Description
This project
includes design, ROW, construction, and construction
administration in two phases for interim and ultimate capacity
improvements to the intersection and vicinity to accommodate
additional turn lanes (both right and left), and additional
through lanes determined through an analysis and projection of
traffic data. Improvements will include: paving, curb, gutter,
driveways, medians, pavement marking, signing and striping,
street lighting, sidewalks, pedestrian access ramps,
landscaping, landscape irrigation and utility relocations. The
traffic signal will be relocated and modified to direct
additional turn lanes and thru lanes. Traffic signal
interconnect conduit and related facilities will be included in
the project.
Project at a Glance
|
Lead Agency |
Arizona
Department of Transportation (ADOT)
|
|
Partner Agency |
City of Peoria
Ben Wilson (Project Manager)
Phone: 623-773-7185
E-mail: Ben.Wilson@PeoriaAz.gov |
|
Design Consultant |
Kimley-Horn &
Associates |
|
Contractor |
N/A |
|
Project Budget |
$3.7 Million |
|
Funding Sources |
General Obligation
Bonds |
Project Status as of
July 2008
The
widening project is anticipated to start in the Spring, 2009.
Utilities, such as SRP Irrigation, SRP Power, APS Power,
Southwest Gas and Cox Communications will be relocated during
the year, 2008. These utilities need to be relocated before the
widening construction can occur.
There will
be on-and-off construction activities beginning from July 2008
through February 2009 prior to the intersection pavement widening.
Lane restrictions will be limited to night-time when possible.
The table
below shows the best information we have at this time for utility
construction schedules. The table will be updated as the project
moves along.
|
Activity
|
Anticipated Activity Duration |
|
Progress of Activity
|
|
Intersection Widening Design |
Finalizing utility relocation coordination |
95% |
|
|
COX relocations |
Relocated as of April 2008 |
100% |
|
|
Activities
above must be completed before Activities below can start |
|
Southwest Gas relocation |
July 2008 |
0% |
|
|
Land Acquisition |
Finalizing Land Acquisition |
40% |
|
|
City waterline relocations |
September
Expect minor
lane restrictions in September. Water lines and hydrants
need to be moved prior to SRP Irrigation can relocate |
0% |
|
|
Activities
above must be completed before Activities below can start |
|
SRP Power relocation |
July – November 2008 |
0% |
|
|
APS Power relocation |
Mid July to August 2008
No lane
restrictions expected |
0% |
|
|
Activities
above must be completed before Activities below can start |
|
SRP Irrigation relocation |
November 2008 – February 2009 |
0% |
|
|
Activities
above must be completed before Activities below can start |
|
Intersection Widening Construction |
April 2009 to December 2009 |
0% |
|
Download
Documents
Last
Updated:
Monday June 30, 2008 01:57 PM
|