87th Avenue; Olive Avenue to Hatcher Road

Project Description
This project is to provide for the design, construction, and right-of-way acquisition required to widen the west half of  87th Avenue between Olive Avenue and Hatcher Road.  This will include pavement, storm drainage, curbs, gutters, driveways and sidewalk improvements. Pavement widening will provide for one lane in each direction with a center two-way left turn lane and bike lanes. No additional widening of
87th Avenue is anticipated on the east side of the road adjacent to the existing subdivision, however; pavement repairs/resurfacing will likely occur.  In addition, this project will construct a 48-inch diameter regional drainage pipe along 87th Avenue from Olive Avenue extending north to just beyond Hatcher Road where it will be plugged for future extension to Mountain View Road. This drainage pipe will not only provide future regional drainage benefits to the Old Town Peoria vicinity, but will provide the needed immediate drainage improvement to help mitigate current nuisance storm drain ponding occurring at the southwest corner of Hatcher Road and 87th Avenue. Additional street lighting is not anticipated at this time as existing lighting improvements along this stretch of roadway currently meets the City of Peoria guidelines.

Project at a Glance

Lead Agency City of Peoria
Richard Costa (Peoria Project Manager)
Phone: 623-773-7951
E-mail:
Richard.costa@PeoriaAz.Gov
Design Consultant To Be Determined
Contractor To Be Determined
Project Budget $1.8 Million
Funding Sources

Transportation Sales Tax

Project Status
The City of Peoria is currently soliciting for a design consultant to complete the needed project design documents for construction.  An Area Drainage Master Plan Update was recently completed in 2007 that provided the City with the necessary regional drainage recommendations which will be incorporated into this project. It is anticipated that the final design will be complete in mid to late 2008, with construction beginning immediately after. During construction, traffic restrictions will be required along 87th Avenue as well at the intersection of 87th Avenue and Olive Avenue to complete a storm drainage connection in Olive Avenue.

Design 0%
25% 50% 75% 100%

 

                                     
Land Acquisition 0%
25% 50% 75% 100%

 

                                     
Construction 0%
25% 50% 75% 100%

 

                                     